Road Work Set to Begin

Road Work Set to Begin

The following is scheduled for next week.  All projects are highly weather dependent, at this time the schedule for Milling is as follows:

Knowland Farm Road 6/19 - 6/20
Pinnacle East 6/21
Spear Street 6/22
Spear Street and Cedar Glenn 6/23
Butler Farm Road 6/26

Paving
Spear Street and Knowland Farm Road 6/26 – 6/28

Please plan accordingly, traffic could be heavy at times.